- 2,900 square yards of 7" pavement
- 2.700 cubic yards of Class 13 excavation
- 1,800 feet of 2.0' curb and gutter
- 675 feet of 8" water main
- 2,300 feet of storm sewer and subdrain
- 1,300 square yards of permeable interlocking pavers
- 7 rain gardens
- 46 stall parking lot
- Sidewalk and driveways as needed
Construction is expected to begin on Monday, June 6, 2016. From this period on, the section of Erie Street between Milwaukee Avenue (Highway 7) and 6th Street will be closed to all traffic for the duration of construction. All homes and businesses will remain accessible via alleyways and arterial streets.